Eskom, Majuba Power Station – Mpumalanga, South Africa

Majuba Power Station Coal Silo Recovery Project.

This system was the permanent reinstatement of the collapsed Silo 20 and associated conveyors. The system included: • Reinstatement of two coal Overland Conveyors: 1.5km at 3260T/h each, including new drive station and take-up and new online elemental analyser

• Installation of a moveable belt plough on each of the overland conveyors to allow for coal to be diverted onto the bypass system if necessary. This plough technology was a first in South Africa

• Reinstatement of the four Oversilo Link Conveyors: 170m at 3260t/h each

• Two new undersilo belt feeders: 21m at 1200t/h each

• Reinstatement of complex and extensive structural steel, including three 30m (70 tons each) gantries, and a transfer house (110 tons), all at a height of 60m above ground

The structural scope included the design and construction of all conveyor support structures, access walkways and staircases, and transfer points.

Time constraints were a major factor and the entire project was completed in 14 months. Creative methods of pre-assembly and rigging, particularly at the top of Silo 20 (approx. 60m high) were key to completing on time.

Turnkey Contractor for the mechanical portion of the works, as part of a two-company Consortium. Rula’s scope included: project management, design and design management, manufacturing, installation and commissioning of the mechanical, structural, electrical, control, instrumentation, fire protection, fire detection and civil engineering works for the described scope

RULA -->