Civil Construction & Concrete Repairs // PPC Dwaalboom

Mill
Fly Ash Feed

Civil construction and remedial concrete works for the silo supporting infrastructure of the Mill Fly Ash Feed installation at PPC Dwaalboom.

Dwaalboom, South Africa
PPC Cement
PDWB-06

Project Stats

Project IDPDWB-06
ClientPPC Ltd
CategoryPPC Cement
LocationDwaalboom, South Africa

Project Overview

Civil construction and remedial concrete works for the silo supporting infrastructure of the Mill Fly Ash Feed installation at PPC Dwaalboom.

// Scope of Work

Scope Of Work

Scope of Work

RULA’s scope covered the complete civil construction activities required to prepare the silo structure for subsequent steel erection. The works included:

  • Setting out and surveying of the silo position and foundation levels
  • Excavation of the silo foundation area in accordance with the approved drawings
  • Preparation and construction of mass-fill concrete foundations
  • Fabrication and installation of reinforcing steel cages
  • Construction of reinforced concrete support columns
  • Installation and accurate positioning of holding-down bolts for the structural steelwork
  • Formwork, concrete placement, vibration, curing and finishing
  • Concrete quality testing and inspection
  • Removal of formwork and final finishing of the completed concrete structure
  • Final inspection and handover of the civil works for steel erection
Silo Column Remedial Works

Following construction, RULA also completed remedial concrete works to areas of honeycombing and voids identified within the silo columns.

The repair process included removing defective concrete back to sound material, cleaning and preparing the exposed surfaces, applying the specified bonding system and reinstating the affected areas using specialised concrete repair material.

The repaired surfaces were finished to provide a consistent and durable final structure.

Quality, Safety & Environmental Management

All construction and repair activities were carried out under controlled quality, safety and environmental procedures.

Quality Control Plans were maintained throughout the works, with inspections and final acceptance completed in conjunction with the client.

The project incorporated competent supervision, task-specific risk assessments, appropriate PPE, controlled excavation areas, responsible waste management and final quality inspections prior to handover.

Project Outcomes

Quality Control: QCP MAINTAINED
Risk Assessments: TASK SPECIFIC
PPE Compliance: MANDATORY
Waste Management: CONTROLLED
Capabilities Delivered